top of page

Tower 500 Garage

IMG_4729 (1).jpg
Parking Update for Tower 500 Residents.png
Spanish Tower 500 parking notice.png

Tower 500 Garage Restoration Project 

The Tower 500 garage restoration project will begin on Monday, February 10th, at 8:30 AM. All vehicles must be removed from the designated work area, which includes all four levels of the garage as part of Phase I. Notices will be placed on vehicles that need to be relocated, and residents who are unable to park on the 4th level will be offered complimentary valet service.

​

Phase I is expected to take approximately 4-6 weeks to complete. Management will keep residents informed and provide updates as the project progresses. For safety reasons, please do not enter any barricaded construction areas at any time. 

 

*Please see below picture of the spaces that need to be moved no later than Friday, February 7th.

Scan2025-02-04_142640 (2).jpg
Garage 500 - Phases 1-4 - Typical Layout Per Floor.png
bottom of page